Jerry Moyer, Court Administrator, has provided this update on courthouse construction:

2nd Floor:

Work on the Elevator and stairwell used for moving prisoners has been
completed.

Good progress is being done on the electrical, plumbing, heating and air
duct installation.   Wall studs and dry wall board is being installed.

Installation of the sprinkler system is also in progress.

Expect to experience noise while all of this work is being done.   

Thank you for your patience!